Schedule

AnnouncedJun 12, 2009
ApprovedJul 28, 2010
2010
Built

Approved 14 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of New Brunswick
Construction start
Aug 4, 2009(actual)
Construction end
Nov 30, 2009(actual)