Back to projects

Highway 101 Interchange Construction

Halifax, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$3.0M
$3,000,000
Federal share33%

of $9.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
20102011
Built

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Sep 14, 2009(actual)
Construction end
Jun 17, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2009

Also in Halifax

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35356 in the federal list. How to read these figures.