Back to projects

Main Street, Louisbourg

Louisbourg, Nova Scotia

completeWastewaterISF
Federal contribution
$44,667
Federal share33%

of $134.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 23, 2009
2010
Built
Program
Infrastructure Stimulus Fund
Construction start
May 5, 2010(actual)
Construction end
Aug 6, 2010(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 31, 2010
  • Construction end8 weeks earlyforecast Sep 30, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35469 in the federal list. How to read these figures.