Liberty Street and Mitchell Street Watermain and Sewer Repairs
Federal contribution
$91,214
Federal share33%
of $274.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Dec 22, 2010(actual)
Against the original forecast
- Construction end2 months earlyforecast Feb 28, 2011
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35519 in the federal list. How to read these figures.