Church Street Sewers
Federal contribution
$101,262
Federal share26%
of $384.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Cape Breton
- Construction start
- May 3, 2010(actual)
- Construction end
- Dec 3, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 31, 2010
- Construction end4 weeks earlyforecast Dec 31, 2010
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35524 in the federal list. How to read these figures.