Highway 125 Repaving
Federal contribution
$225,000
Federal share50%
of $450.0K total eligible cost; the rest comes from other partners.
Approved 4 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Sep 10, 2009(actual)
- Construction end
- Sep 25, 2009(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 15, 2009
- Construction end5 weeks earlyforecast Oct 30, 2009
Also in Cape Breton
- Cape Breton Regional Municipality - Wastewater Treatment Infrastructure$39.2M
- Cape Breton University - Centre for Discovery and Innovation$20.0M
- Eskasoni First Nation Long Term Care Kiknu$19.7M
- Sydney Harbour West Wastewater Collection and Treatment$19.3M
- CBRM - Battery Electric Bus Purchase and Storage and Maintenance Facility - Phase 2$16.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35578 in the federal list. How to read these figures.