Back to projects

Highway 125 Repaving

Cape Breton, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$225,000
Federal share50%

of $450.0K total eligible cost; the rest comes from other partners.

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Sep 10, 2009(actual)
Construction end
Sep 25, 2009(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 15, 2009
  • Construction end5 weeks earlyforecast Oct 30, 2009

Also in Cape Breton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35578 in the federal list. How to read these figures.