Setting Up of Orléans-Cumberland Community Resource Centre
Federal contribution
$250,000
Federal share33%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 21, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Orléans-Cumberland Community Resource Centre
- Construction start
- May 3, 2010(actual)
- Construction end
- Nov 15, 2010(actual)
Against the original forecast
- Construction start7 months lateforecast Oct 1, 2009
- Construction end7 weeks lateforecast Sep 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35581 in the federal list. How to read these figures.