Roundabout Construction and Ramp Modifications on Route 327

Cape Breton, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$450,000
Federal share50%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
Built

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Sep 4, 2009(actual)
Construction end
Dec 17, 2009(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 1, 2009
  • Construction end7 weeks lateforecast Oct 31, 2009