Trunk 4 Repaving from Lakeshore Drive West

Richmond, Nova Scotia

completeHighways and RoadsISF
Federal contribution
$720,000
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
Built

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Nova Scotia
Construction start
Aug 10, 2009(actual)
Construction end
Nov 15, 2009(actual)

Against the original forecast

  • Construction end2 weeks lateforecast Oct 31, 2009