Construction of a sports complex
Federal contribution
$10.0M
$9,984,720
Federal share33%
of $30.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 27, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Westmount
- Construction start
- Aug 1, 2010(actual)
- Construction end
- Mar 31, 2011(actual)
Also in Westmount
- Program for the renewal of drinking water and wastewater pipes$926.0K
- Program for the renewal of drinking water and wastewater pipes$294.2K
- Repairs and upgrading of sanitary infrastructure$235.1K
- Program for the renewal of drinking water and wastewater pipes$206.3K
- Upgrading of exterior landscaping elements$195.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35729 in the federal list. How to read these figures.