Pavement reinforcement on Highway 335
Federal contribution
$707,581
Federal share49%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 5, 2010(actual)
- Construction end
- Nov 3, 2010(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2010
- Construction end4 weeks earlyforecast Nov 30, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35776 in the federal list. How to read these figures.