Repairs to Blue Sea Road North in Blue Sea
Federal contribution
$835,000
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Nov 29, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 1, 2010
- Construction end2 weeks earlyforecast Dec 15, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35777 in the federal list. How to read these figures.