Repairs to Highway 143 in Stanstead-Est
Federal contribution
$628,132
Federal share46%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 9, 2010(actual)
- Construction end
- Sep 16, 2010(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jun 30, 2010
- Construction end6 weeks earlyforecast Oct 31, 2010
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35786 in the federal list. How to read these figures.