Repairs to Highway 117 in Moncerf-Lytton

Montcerf-Lytton, Quebec

completeHighways and RoadsISF
Federal contribution
$1.1M
$1,050,000
Federal share50%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 14, 2010(actual)
Construction end
Jun 29, 2011(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Jul 15, 2011