Repairs to Highway 105 in La Pêche
Federal contribution
$735,990
Federal share47%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 6, 2010(actual)
- Construction end
- Oct 25, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 15, 2010
- Construction end3 weeks lateforecast Oct 1, 2010