Red Lodge Water Treatment Plant Upgrade

Bowden, Alberta

completeDrinking WaterISF
Federal contribution
$133,629
Federal share45%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Apr 1, 2010(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 months earlyforecast Jul 1, 2010