Residential Development - Bullard Site

Saint-Jean-de-Brébeuf, Quebec

completeWastewaterISF
Federal contribution
$154,352
Federal share13%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 15, 2011(actual)
Construction end
Oct 31, 2011(actual)