Extension of the Sanitary Sewer System on Route 204

Audet, Quebec

completeWastewaterISF
Federal contribution
$200,355
Federal share33%

of $601.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Municipality of Audet
Construction start
Sep 20, 2010(actual)
Construction end
Aug 1, 2011(actual)