Schedule

AnnouncedAug 27, 2009
ApprovedJan 26, 2010
2010
Built

Approved 5 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 30, 2010(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Aug 1, 2010
  • Construction end7 weeks earlyforecast Jan 15, 2011

Also in Saint-Adrien-d'Irlande