Bridge Replacement
Poplar Valley No. 12, Saskatchewan
Federal contribution
$28,122
Federal share28%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Sep 21, 2009(actual)
- Construction end
- Oct 30, 2009(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Oct 5, 2009
- Construction end5 months earlyforecast Mar 31, 2010
Also in Poplar Valley No. 12
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35922 in the federal list. How to read these figures.