Bridge Replacement in the Rural Municipality of Moose Range
Moose Range No. 486, Saskatchewan
Federal contribution
$33,333
Federal share33%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Nov 6, 2009(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2010
Also in Moose Range No. 486