Bridge Replacement in Milden
Federal contribution
$29,165
Federal share29%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJan 27, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Saskatchewan
- Construction start
- Oct 13, 2009(actual)
- Construction end
- Nov 9, 2009(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Dec 11, 2009
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35932 in the federal list. How to read these figures.