Resurfacing Route 169 between Val-Jalbert and Chambord - Phase 2
Federal contribution
$526,321
Federal share39%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedOct 2, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Aug 26, 2010(actual)
- Construction end
- Sep 9, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 15, 2010
- Construction end6 weeks lateforecast Jul 31, 2011