Resurfacing Route 169 between Val-Jalbert and Chambord - Phase 2

Chambord, Quebec

completeHighways and RoadsISF
Federal contribution
$526,321
Federal share39%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 2, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 26, 2010(actual)
Construction end
Sep 9, 2011(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 15, 2010
  • Construction end6 weeks lateforecast Jul 31, 2011