Resurfacing Highway 113
Federal contribution
$1.6M
$1,580,116
Federal share43%
of $3.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Jun 7, 2010(actual)
- Construction end
- Aug 8, 2010(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Sep 30, 2010