Rebuilding Main Street

Saint-Rémi-de-Tingwick, Quebec

completeHighways and RoadsISF
Federal contribution
$666,474
Federal share44%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 2, 2010(actual)
Construction end
Nov 18, 2010(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 15, 2010
  • Construction end3 weeks lateforecast Oct 31, 2010

Also in Saint-Rémi-de-Tingwick

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35949 in the federal list. How to read these figures.