Repairs to Highway 293 in the Municipality of St Cyprien
Federal contribution
$755,000
Federal share50%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Oct 3, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 13, 2010
- Construction end4 weeks earlyforecast Oct 31, 2011
Also in Saint-Cyprien