Resurfacing and paving the roadway shoulders on Highway 169 in the territory of Lac Jacques Cartier
Federal contribution
$831,000
Federal share50%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built
Approved 4 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Quebec
- Construction start
- Oct 18, 2010(actual)
- Construction end
- Jul 14, 2011(actual)
Against the original forecast
- Construction start7 months earlyforecast Jun 1, 2011
- Construction end7 weeks earlyforecast Aug 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35966 in the federal list. How to read these figures.