Back to projects

Roadway Repairs on Highway 291

Saint-Honoré-de-Témiscouata, Quebec

completeHighways and RoadsISF
Federal contribution
$493,857
Federal share43%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Aug 12, 2010(actual)
Construction end
Sep 2, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 15, 2010
  • Construction end3 weeks earlyforecast Sep 24, 2010