New Well and Reverse Osmosis

Vibank, Saskatchewan

completeDrinking WaterMRIF
Federal contribution
$503,333
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 25, 2009
2010201120122013
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Vibank
Construction start
Sep 24, 2009(actual)
Construction end
Feb 1, 2013(actual)

Against the original forecast

  • Construction start7 months lateforecast Feb 24, 2009
  • Construction end8 weeks earlyforecast Mar 31, 2013

Also in Vibank

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 35978 in the federal list. How to read these figures.