completeHighways and RoadsISF
Federal contribution
$3.4M
$3,360,000
Federal share50%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Oct 22, 2010(actual)
Construction end
Aug 26, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Sep 15, 2010
  • Construction end2 months earlyforecast Oct 31, 2011