Bridge Reconstruction on Highway 172

Saint-Ambroise, Quebec

completeHighways and RoadsISF
Federal contribution
$805,639
Federal share29%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
Jun 6, 2010(actual)
Construction end
Jun 29, 2011(actual)

Also in Saint-Ambroise

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36554 in the federal list. How to read these figures.