Bridge Reconstruction on Highway 113

Eeyou Istchee Baie-James, Quebec

completeHighways and RoadsISF
Federal contribution
$1.8M
$1,808,917
Federal share41%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 13, 2009
ApprovedJan 26, 2010
20102011
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Quebec
Construction start
May 29, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36568 in the federal list. How to read these figures.