Resurfacing of Highway 33 from Swan Hills to South of 18th Baseline
Federal contribution
$5.8M
$5,754,924
Federal share50%
of $11.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Jun 6, 2010(actual)
- Construction end
- May 25, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 1, 2010
- Construction end5 months earlyforecast Oct 15, 2011
Also in Swan Hills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36618 in the federal list. How to read these figures.