Resurfacing of Highway 33 from Swan Hills to South of 18th Baseline

Swan Hills, Alberta

completeHighways and RoadsISF
Federal contribution
$5.8M
$5,754,924
Federal share50%

of $11.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
20102011
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Jun 6, 2010(actual)
Construction end
May 25, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2010
  • Construction end5 months earlyforecast Oct 15, 2011