Resurfacing Urban Access Road 108 - Cadogan Access

Cadogan, Alberta

completeHighways and RoadsISF
Federal contribution
$347,271
Federal share50%

of $694.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Apr 30, 2010(actual)
Construction end
Jul 9, 2010(actual)

Against the original forecast

  • Construction end9 months earlyforecast Mar 31, 2011

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36625 in the federal list. How to read these figures.