Back to projects

Highway 22 Improvements

Mayerthorpe, Alberta

completeHighways and RoadsISF
Federal contribution
$182,202
Federal share50%

of $364.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedSep 24, 2009
ApprovedJul 23, 2010
2010
Built

Approved 10 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Alberta
Construction start
Aug 15, 2010(actual)
Construction end
Sep 25, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2010
  • Construction end6 months earlyforecast Mar 31, 2011

Also in Mayerthorpe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36629 in the federal list. How to read these figures.