Highway 602 Improvements
Federal contribution
$165,695
Federal share49%
of $340.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedJul 23, 2010
2010
Built
Approved 10 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Alberta
- Construction start
- Apr 14, 2010(actual)
- Construction end
- Aug 11, 2010(actual)
Against the original forecast
- Construction start2 weeks earlyforecast May 1, 2010
- Construction end8 months earlyforecast Mar 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36634 in the federal list. How to read these figures.