Back to projects

Wastewater collection and treatment

Ravignan, Quebec

completeWastewaterCC
Federal contribution
$1.2M
$1,221,251
Federal share46%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 15, 2009
2010201220142016
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
May 24, 2011(actual)
Construction end
Jan 18, 2017(actual)

Against the original forecast

  • Construction start3.9 years earlyforecast Apr 1, 2015
  • Construction end13 months lateforecast Dec 31, 2015

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36704 in the federal list. How to read these figures.