Industrial Park Development - Municipal Infrastructure

Sainte-Clotilde-de-Beauce, Quebec

completeHighways and RoadsISF
Federal contribution
$126,402
Federal share33%

of $386.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedOct 2, 2009
ApprovedJan 26, 2010
2010
Built

Approved 4 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 4, 2010(actual)
Construction end
Dec 11, 2010(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Jan 15, 2011