Overpass Construction on Highway 102
Federal contribution
$3.3M
$3,333,333
Federal share33%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Mar 22, 2010(actual)
- Construction end
- Oct 27, 2011(actual)