Captain William Spry Centre and Former Dartmouth City Hall Rehabilitation
Federal contribution
$179,542
Federal share29%
of $610.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction end6 months lateforecast Mar 31, 2011