Roof Replacement - Otter Lake Landfill
Federal contribution
$1.0M
$1,000,000
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- May 12, 2010(actual)
- Construction end
- Dec 6, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 31, 2010
- Construction end3 weeks lateforecast Nov 15, 2010
Also in Halifax