Lebourdais Avenue Improvements
Federal contribution
$187,500
Federal share33%
of $562.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedOct 16, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Village of Clinton
- Construction start
- May 31, 2010(actual)
- Construction end
- Oct 8, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 15, 2010
- Construction end3 weeks lateforecast Sep 15, 2010