Phase 1 of modernization of water production system
Federal contribution
$127,087
Federal share25%
of $508.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 20, 2009
201020112012
Built
Approved 2 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Parish of La Doré
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Oct 24, 2012(actual)
Against the original forecast
- Construction start2 weeks lateforecast Feb 15, 2010
- Construction end23 months lateforecast Nov 15, 2010
Also in La Doré
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36807 in the federal list. How to read these figures.