Upgrading the British Columbia Museum of Mining
Britannia Beach, British Columbia
Federal contribution
$1.0M
$1,000,000
Federal share34%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 24, 2009
20102011
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Britannia Beach Historical Society
- Construction start
- Dec 15, 2009(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 30, 2009
- Construction end4 weeks earlyforecast Oct 31, 2011
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36839 in the federal list. How to read these figures.