Burnside/North Dartmouth Trunk Sewer Extension

Halifax, Nova Scotia

completeWastewaterISF
Federal contribution
$1.3M
$1,267,373
Federal share32%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Jul 5, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 30, 2011