Clearview Heights Sanitary Sewer
Federal contribution
$419,259
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedSep 24, 2009
ApprovedOct 16, 2009
2010
Built
Approved 3 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Revelstoke
- Construction start
- Jul 12, 2010(actual)
- Construction end
- Oct 3, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 12, 2010
- Construction end6 months earlyforecast Mar 26, 2011