Back to projects

City Hall Restoration

Halifax, Nova Scotia

completeAdministration, Emergency and Public WorksISF
Federal contribution
$562,637
Federal share28%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
May 6, 2010(actual)
Construction end
Apr 4, 2011(actual)

Also in Halifax