Chester Spur Line Regional Trails
Federal contribution
$306,286
Federal share31%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
2010
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Aug 3, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 30, 2010
- Construction end2 weeks earlyforecast Dec 15, 2010
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 36852 in the federal list. How to read these figures.