Back to projects

Hubley Fire Station

Halifax, Nova Scotia

completeAdministration, Emergency and Public WorksISF
Federal contribution
$825,705
Federal share28%

of $3.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 13, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Construction start
Jul 1, 2010(actual)
Construction end
Mar 23, 2011(actual)

Also in Halifax