Joseph Howe Overpass
Federal contribution
$652,733
Federal share47%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 13, 2009
20102011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Nova Scotia
- Construction start
- Nov 12, 2009(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Sep 15, 2009
- Construction end4 weeks lateforecast May 31, 2011